Oil India · OIL

Oil India's new crude pipeline slips again, and full use of the bigger refinery moves to 2029

Oil India's fields are producing what management guided, but the Paradip–Numaligarh pipeline and the refinery expansion it feeds now carry later dates than management gave in 2025 and February 2026.

3 min read Published on

Published by

Inve Content team

Oil India stock page → More news from 16 Nov 2026

On 13 November, Oil India said the crude oil pipeline it is building from Paradip to Numaligarh would miss the December date management gave in August. The line is meant to feed the expansion of the Numaligarh refinery, run by its subsidiary NRL, and the refinery's ramp-up has also slipped: management now expects to use all of the added capacity in 2029.

Abhijit Das, the chief investor relations officer, said: "we had given a date of December. But we may feel that we are feeling that there will be a little bit spill over". All but the last 40 kilometres of the line are complete, he said, and the company is aiming for mechanical completion by March 2027. December was not the first date to slip. On the May 2025 call management expected the line to be commissioned in October 2025, and in February 2026 it said the line would be ready for commissioning by June 2026.

The refinery's timetable has drifted in the same direction. NRL is tripling the refinery's capacity. In February 2026 management guided that it would run at full capacity by September 2027; in August it spoke of three-quarters of the enlarged refinery's rated capacity by March 2028. This time Das said about half of the added capacity would be in use by December 2027, and all of it in 2029. The bases differ, since the earlier guidance described the whole refinery and the latest describes only the new capacity, but on the figures as given the date for full use has moved from 2027 into 2029.

None of this has reached the oil fields, which are doing what management said they would. Crude production in the September 2026 quarter was well above a year earlier and reached the pace of about 1 million tonnes a quarter that management guided in August, when it put FY27 output at a minimum of 3.9 million tonnes. Abhijit Majumder, director (finance), tied the volume to drilling: "This year, the internal target is to drill 100 wells." That is more than the company drilled last year.

Crude output reached the million-tonne-a-quarter pace management guided in August

MMT

Crude oil production

  1. 0.85 MMT Q2 FY26
  2. 0.95 MMT Q1 FY27
  3. 1.021 MMT Q2 FY27
Oil India standalone crude production by quarter.

Those barrels, sold at about $92 a barrel against $68 a year earlier, carry the profit. Oil India's standalone operating margin, which excludes NRL, stayed well above the level of a year earlier last quarter but fell back sharply from the quarter before. Part of that fall is exploration. Bineet Banka of Nomura put the quarter's write-offs of dry wells at ₹1,480 crore, against a usual ₹700 crore to ₹800 crore.

Operating margin fell back from the quarter before but stayed above a year earlier

%

Standalone operating margin

  1. 24.3% Q2 FY26
  2. 51.3% Q1 FY27
  3. 37.2% Q2 FY27
Operating profit as a share of sales, Oil India standalone.

Another write-off may follow. A third well in the company's Andaman offshore campaign is still carried as an asset. Das said it has not been written off yet, but that the company will decide whether to keep it or write it off once study results from new seismic surveys arrive, which it expects by January. Majumder said that well would cost ₹850 crore to ₹900 crore if it is written off.

Gas looks more like the pipeline than the oil. Output last quarter was slightly below a year earlier, and guidance for FY27 has come down since August 2025. Das said the constraint is connecting the fields to the lines that carry gas out, which the company is trying to fix within another 18 to 20 months.

FY27 gas guidance has come down at each update since August 2025

bcm

  1. Guided August 2025 4.31 bcm
  2. Guided November 2025 3.8 bcm
  3. Guided May 2026 3.35 bcm
Natural gas production guidance for the year to March 2027, as given on each call.

So the profit holders see today comes from the existing fields, helped by oil prices, while the pipeline and the larger refinery keep arriving later than guided. One date has held: since May 2026 management has said the whole refinery expansion will be finished by March 2027, after guiding commissioning from December 2025 on the 2025 calls.

Oil India stock page →

The record: full financial tables

Financials

Income statement, last 8 quarters

₹ crore; YoY and margin in %
Quarter endSalesYoYOperating profitOp. marginOther incomePBTNet profit
Sept 20268,071+47.9%3,00137.2%8452,8672,259
Jun 20267,958+58.8%4,08451.3%5213,7422,870
Mar 20265,961+8.0%1,82130.5%1,1392,0571,790
Dec 20254,916−6.2%1,30826.6%547948808
Sept 20255,457+4.0%1,32524.3%8311,3181,044
Jun 20255,012−6.0%1,60632.0%1761,098813
Mar 20255,519−0.1%1,98435.9%6642,0201,591
Dec 20245,240−1.6%2,13340.7%1891,5501,222

Balance sheet

₹ crore
As ofEquityDebtInvestmentsFixed assetsCWIPTotal assets
Sept 202653,26115,98837,47624,8823,88880,720
Mar 202648,52614,74736,37423,7383,44576,743
Sept 202556,25835,85436,89024,70732,6951,16,908
Mar 202545,43512,88635,17019,3853,33669,698

Cash flow

₹ crore
Year endOperatingInvestingFinancingFree cash flow
Mar 20267,576−3,840−3,5656,624
Mar 20258,171−5,233−2,7827,058
Mar 20247,715−4,945−2,7767,005
Mar 20237,660−3,593−4,2207,029