NHPC sets an FY28 profit target that hangs on late dams and pending tariff orders

A new dam, a restored one and a far better quarter at Parbati-II lifted NHPC's quarterly profit by almost two-thirds; management now targets ₹6,000-6,400 crore of profit for FY28, but the plants and tariff orders it needs have run behind earlier dates.

4 min read Published on

Published by

Inve Content team

Nhpc stock page → More news from 10 Nov 2026

NHPC, the state-owned hydropower producer, sells electricity from its dams at tariffs the Central Electricity Regulatory Commission sets to give a return on the equity invested in each plant. Until recently much of its capital sat in projects still under construction. In the September 2026 quarter the filed results showed that changing: standalone sales rose 51.0% from a year earlier, and profit after tax rose 64.7% to ₹1,525 crore.

The shift is plain on the balance sheet. Over the past year and a half the value of plant still being built roughly halved, while plant in service rose about two and a half times. Management credited four stations for most of the rise in profit: Subansiri Lower, Parbati-II, Parbati-III and Teesta-V, which resumed commercial operation after being restored.

In 18 months, more of NHPC's capital moved from building sites into plants that earn

₹ cr

Plant in service

  1. ₹19,285 crore Mar 2025
  2. ₹48,376 crore Sep 2026

Under construction

  1. ₹40,037 crore Mar 2025
  2. ₹20,770 crore Sep 2026
Standalone balance sheet; plant under construction is capital work in progress.

Running plants also widened the margin. Operating profit, measured before interest, depreciation and other income, was 63.6% of standalone sales last quarter, against 55.6% a year earlier. A finished plant brings its own costs into the income statement, though: once a unit runs, the interest on the money borrowed to build it and the depreciation of the asset are charged against profit. Interest roughly doubled from a year earlier and depreciation also climbed. Calculated from the filed results, the two together took back about two-fifths of the rise in operating profit, leaving profit before tax ₹760 crore higher. Other income rose far less, so most of the gain came from operations.

Operating profit drove the pre-tax gain; interest and depreciation took back about two-fifths of its rise

₹ cr

  1. Operating profit 1106
  2. Other income 106
  3. Interest -283
  4. Depreciation -168
  5. Profit before tax 760
Change from a year earlier, standalone, calculated from the filed results.

Standalone profit before tax for the first half of this fiscal year already exceeded the whole of the previous year's. That flatters the run rate, because the first half is the wet season: management said most of a year's hydro generation comes in those six months, on a five-year average.

Part of the new revenue is also provisional. For Subansiri Lower and Parbati-II, NHPC books revenue at 80% of the tariff it has asked the regulator to approve; for Parbati-II alone, the unbooked remainder comes to ₹500 crore, management said. The date for settling it has moved. In February management expected the regulator's final order on Parbati-II within five to six months; in May it said by the end of June. The next hearing is set for 11 November, and Mahesh Sharma, the director of finance, said: "we hope that this will be the final hearing, and thereafter order will be reserved."

Management has now put a number on where the build-out leads. Asked about funding, Sanjay Singh, the director of projects, said NHPC is targeting profit after tax of ₹6,000-6,400 crore in the fiscal year to March 2028, and EBITDA (earnings before interest, tax, depreciation and amortisation) of ₹10,000 crore once Subansiri Lower runs a full year and Pakal Dul is running.

Management's profit target for the year to March 2028 sits well above last year's standalone profit

₹ cr

  1. Profit after tax, previous fiscal year ₹3,619 crore
  2. Profit after tax, first half of this year ₹2,638 crore
  3. Target, low end ₹6,000 crore
Inve's figures are standalone; the target is management's.

That target depends on plants arriving when management now says they will, and the dates have moved before. In May 2025 the company expected all eight Subansiri Lower units to be running by May 2026; the last is now due by June 2027. Pakal Dul, then guided for September 2026, is now expected to be fully commissioned by that same June. Two solar plants that were due in June and December 2026 are now expected in January and November next year, which management put down to problems connecting them to the grid.

Delay need not cost NHPC everything it adds to a project: the regulator's rules let cost overruns beyond management's control pass through to tariffs, the company said in May 2026. Some of the slippage, such as grid connections for the solar plants, sits outside NHPC's hands. What delay moves is timing: the finished units already carry their interest and depreciation, while part of their revenue waits on orders and the plants needed for the target are still being built. The next markers are this month's Parbati-II hearing and the interim tariff for Subansiri Lower, where the hearing is over and the order reserved.

Nhpc stock page →

The record: full financial tables

Financials

Income statement, last 8 quarters

₹ crore; YoY and margin in %
Quarter endSalesYoYOperating profitOp. marginOther incomePBTNet profit
Sept 20264,125+51.0%2,62463.6%4861,9691,525
Jun 20263,537+18.8%2,16661.2%4491,4351,113
Mar 20262,741+33.1%78528.6%375−451,328
Dec 20251,877−4.7%−32−1.7%1,567797293
Sept 20252,732+7.2%1,51855.6%3801,209926
Jun 20252,977+23.2%1,64655.3%4121,3911,072
Mar 20252,059+24.9%1,03450.2%3061,077894
Dec 20241,970+16.2%79040.1%479338274

Balance sheet

₹ crore
As ofEquityDebtInvestmentsFixed assetsCWIPTotal assets
Sept 202642,27647,7066,41448,37620,7701,05,192
Mar 202639,97244,3076,38847,44519,27198,468
Sept 202541,24044,92344835,69042,9751,11,563
Mar 202538,34836,0025,92619,28540,03787,127

Cash flow

₹ crore
Year endOperatingInvestingFinancingFree cash flow
Mar 20262,349−5,6823,714−3,845
Mar 20254,160−4,412−87−334
Mar 20246,128−3,797−1,8451,925
Mar 20233,907−2,929−1,5201,140